New York Gas Plant Comes Online Despite Opposition

The Valley Energy Center in Orange County, New York, entered commercial operation on October 1 despite complaints from local officials and area residents about noise from the plant, among other concerns. Community members spoke out against the plant at public hearings last week, saying they have felt sick when the plant has undergone test runs […]

The post New York Gas Plant Comes Online Despite Opposition appeared first on POWER Magazine.

Read more

Judge Rules New York Gas Plant Can Resume Startup Tests

A New York Supreme Court judge on August 15 said Competitive Power Ventures (CPV) can resume startup tests at its new natural gas-fired power plant in Wawayanda. The decision Wednesday from Judge Roger D. McDonough came one day after CPV sued New York’s Department of Environmental Conservation (DEC). CPV is seeking an injunction allowing it […]

The post Judge Rules New York Gas Plant Can Resume Startup Tests appeared first on POWER Magazine.

Read more

New York Denies Air Permit for New Gas-Fired Power Plant

A natural gas-fired power plant in New York state that planned to ramp up to full operations this month has been denied an air quality permit from state officials. Competitive Power Ventures’ (CPV’s) Valley Energy Center in Wawayanda, located in Orange County north of New York City, is in the final testing and commissioning phase, […]

The post New York Denies Air Permit for New Gas-Fired Power Plant appeared first on POWER Magazine.