Vogtle 3 Reaches Initial Criticality, Marking Pivotal Nuclear Startup Milestone

Credit to Author: Sonal Patel| Date: Mon, 06 Mar 2023 23:59:35 +0000

Vogtle 3, one of two 1,117-MW Westinghouse AP1000 nuclear reactors Southern Nuclear Operating Co. is building in Georgia, has reached initial criticality. The event marks a pivotal milestone for the Generation III+ pressurized water reactor (PWR)—the first of its kind built in the U.S.

“Initial criticality is a key step during the startup testing sequence and demonstrates that—for the first time—operators have safely started the nuclear reaction inside the reactor,” Georgia Power, a Southern Co. subsidiary, on March 6. Georgia Power co-owns the Vogtle expansion, comprising Vogte 3 and 4 with Oglethorpe Power, MEAG Power, and Dalton Utilities. “This means atoms are being split and nuclear heat is being made, which will be used to produce steam.”

The reactor now continues startup testing to demonstrate the integrated operation of the primary coolant system and steam supply system at design temperature and pressure with fuel inside the reactor. “Now that the Unit 3 reactor has reached criticality, operators will continue to raise power to support synchronizing the generator to the electric grid and begin producing electricity,” Georgia Power said. “Then, operators will continue increasing power through multiple steps, ultimately raising power to 100%.”

The tests will ensure all systems operate successfully together. They will also validate operating procedures. The unit will be declared commercially operational if the tests are successfully completed. According to Georgia Power, the in-service date for Unit 3 is projected “during May or June 2023.”

As POWER recently reported, Southern Co. anticipates the projected schedule for Unit 3 primarily depends on the progression of final component and pre-operational testing and startup, “which may be impacted by further equipment, component, and/or other operational challenges.” The delays could also affect the in-service date for Unit 4. According to Southern Co.’s Feb. 16–issued annual report, Unit 4 is slated to be placed in service during the late fourth quarter of 2023 or in the first quarter of 2024.

“We remain focused on safely bringing this unit online, fully addressing any issues and getting it right at every level,” said Chris Womack, chairman, president, and CEO of Georgia Power, on Monday. “Reaching initial criticality is one of the final steps in the startup process and has required tremendous diligence and attention to detail from our teams,” he added.

“When you consider the history of safe and reliable operations at Vogtle Units 1 and 2 for decades now, it puts today’s milestone in perspective that Plant Vogtle will be a four-unit site making it the largest of its kind in the U.S. This is a truly exciting time as we prepare to bring online a new nuclear unit that will serve our state with clean and emission-free energy for the next 60 to 80 years,” Womack said. 

Plant Vogtle Units 3 and 4 are the first nuclear plants to be built in the United States in 30 years. This photo shows Vogtle 3 under construction in January 2023. Georgia Power has curated a photographic history of the project here. Courtesy: Georgia Power

The Long Journey to the Major Milestone

The milestone is the latest of several achievements Southern Nuclear has accomplished over the massive project’s timeframe to develop and build Vogtle 3 and 4. Construction of the two reactors (Vogtle 3 and 4)— the first new nuclear units built in the U.S. in the last three decades—kicked off in 2009, with plans to put the reactors online by 2016 and 2017. Four utilities share the project’s ownership interests: Southern Co.’s Georgia Power subsidiary (45.7%); Oglethorpe Power Corp. (OPC, 30%), Municipal Electric Authority of Georgia (MEAG, 22.7%), and Dalton Utilities (1.6%).

Delays, however, have reportedly pushed project costs up to at least $30.3 billion. Costs reported by MEAG in May 2022 suggested total spending for the expansion was close to $34 billion. Southern Co., in its latest annual report, projected Georgia Power’s share of the full capital cost forecast to complete Plant Vogtle Units 3 and 4, including contingency, through the end of the second quarter of 2023 and the first quarter of 2024, respectively, will be $10.6 billion. 

Oglethorpe and Dalton over the summer separately chose to freeze spending on the project, exercising an option all four owners agreed to in 2018. In October 2022, Georgia Power settled a lawsuit with MEAG Power, agreeing to pay at least $76 million based on the current capital cost forecast for completing the project’s construction.

Despite these setbacks, the project has celebrated significant construction and regulatory triumphs. In August 2022, the NRC gave Vogtle 3 a historic 103(g) finding, effectively making Vogtle 3 the first reactor in the nation to reach the milestone as part of the regulator’s Part 52 combined license process. “Shortly after receiving this key finding from the NRC, all 157 fuel assemblies necessary for the safe and reliable startup of the unit were loaded into the reactor core,” Georgia Power noted.

‘An Incredible Moment’ for Westinghouse

Westinghouse in a statement on Monday hailed the milestone. “We are honored to share this incredible moment with Southern Nuclear, Georgia Power, and the project’s co-owners, and with the entire team at Vogtle,” said Patrick Fragman, Westinghouse president and CEO. 

The reactor manufacturer—which supplied the world’s first commercial PWR in 1957—noted four AP1000 units currently operating in China “are currently setting operational performance records.” Four additional AP1000 reactors are under construction in China, and two more are planned. “Poland recently selected the AP1000 reactor for its nuclear energy program, nine units have been announced for Ukraine, and the technology is under consideration at multiple other sites in Central and Eastern Europe, the United Kingdom, and in the United States,” Westinghouse said.

At Vogtle, Westinghouse now plans to “work closely with the team,” readying for the project’s next major milestone: synchronizing the unit to the electric grid. That milestone will be followed by full commercial operation, the company noted. 

Sonal Patel is a POWER senior associate editor (@sonalcpatel@POWERmagazine).

Editor’s note: Updated: March 6, 8:10 p.m. CST.

The post Vogtle 3 Reaches Initial Criticality, Marking Pivotal Nuclear Startup Milestone appeared first on POWER Magazine.

https://www.powermag.com/feed/